Plumbing rough-in

Not a huge amount to report unfortunately.  The roof isn’t on yet – the SS has advised that we are waiting on something roof-frame related to be signed off by the engineer (or surveyor or someone) before they start loading the tiles on.

Apparently the windows were still on schedule for this week but they haven’t been delivered as yet.  The windows are holding up the bricks being done so hopefully we see some action on this next week.  The steel beam that we noticed at the block – which then disappeared – has been replaced with a wider version so it seems that the initial one was incorrect.  I understand that this goes above the sliding doors in the rumpus.

However, the plumbing has been ‘roughed-in’ – all the pipes connected to the various points, including the external tap points. So that was good to see!